During the period of July 2021, we also did restoration of two 400kV Twin Lines at Jharkhand and Maharastra for Adani Transmission and NHAI. 1) 400 KV D/C (Twin) LILO of both circuits of Ranchi – Maithon at Dhanbad ADANI Jharkhand 2) Height raising of 400KV D/C...
Our EPC Projects Division achieved significant milestones in July.They completed successful completion of three 33/11kV substations along with 33kV line connecting the same in Tripura. The inauguration was done in all three cases by Honourable Dy. Chief Minister of...